Location: Saskatoon
Risk: Level III Remediation
Material: Drywall with mold growth and batt insulation in ceiling
Challenges: High ceiling 14′ – Weekend and Evening scheduled work only – Open space and limited ventilation
PPE (Personal Protective Equipment): Full face mask with P100 filters, disposable cover-alls, disposable nitrile gloves
Equipment: Negative air machine 1800 CFM – Air Scrubber 1200 CFM Variable Speed – HEPA Vacuums
Solutions: On site construction of scaffolding on wheels, containment built to isolate working area from processing facility.
Duration: 2 Days, Saturday and Sunday work